Handover and Construction
No handover date exists for Nawayef South. Nawayef East is scheduled for December 2028, 49 months after its launch, and Modon awarded the AED 5 billion main contract for the east and west hills' 735 villas on Dec 19, 2025, about AED 6.8M of construction per villa by our arithmetic.
The latest construction news for Nawayef is nearly a year old: on Dec 19, 2025 Modon awarded the main contract to build the villas of Nawayef East and Nawayef West. Modon has published no progress update since, and no handover date at all for Nawayef South. The street in this clip is still a render.
The dates on record
| Hudayriyat masterplan revealed | Jun 13, 2023, with 18 months of enabling works planned |
| Nawayef West films published | Jun 25, 2024 |
| Nawayef East launched | Nov 7, 2024 |
| Infrastructure contract for both hills | Before Dec 19, 2025, date not given |
| Main construction contract for both hills | Dec 19, 2025 |
| Nawayef East handover | December 2028, per Modon's page |
| Nawayef West handover | Not on modon.com |
| Nawayef South handover | Not published |
The contract, in numbers
Modon's release gives the contract as AED 5 billion for 735 villas of 350 to 2,700 sq m, and calls it the largest residential construction contract awarded in Abu Dhabi in 2025. It does not name the contractor.
Divided out, that is about AED 6.8 million of main-contract construction per villa on average. The figure is ours and it is only an average: the same contract covers a 370 sq m Home and a mansion seven times its size. It is still a useful yardstick beside the east hill's AED 6.6M starting price, because it shows how much of the money on these hills goes into building them.
The timeline, measured
Three intervals can be read off the dates above.
- Launch to handover: Nov 2024 to Dec 2028 is 49 months for the east hill.
- Launch to main contract: the east hill's contract came 13 months after its launch.
- Main contract to handover: that leaves 36 months to build, from Dec 2025 to Dec 2028.
If Nawayef South followed the east hill's intervals exactly from a December 2026 launch, its main contract would come around January 2028 and its handover around January 2031. That is arithmetic, not a schedule: Modon has said nothing, and the island's newer communities are listed with handovers between Q3 2030 (Hudayriyat Golf Estates) and Q2 2031 (Wadeem Gardens), roughly 48 to 56 months after their launches.
We think South's handover will be announced for 2030, a shorter wait than the east hill's, because the hill's roads and services can extend those already contracted for its neighbors.
Why the handover date matters twice
On the east hill's 40/60 plan the final 60% of the price is due on handover (Payment Plan). The date therefore sets both when a buyer gets a house and when the largest payment falls due. Modon's east hill page states the month; the installments before it are in the sale agreement.
Sources
- Modon awards the largest residential construction contract in Abu Dhabi in 2025, Modon, Dec 19, 2025
- Nawayef East, Modon, read Nov 12, 2026
- Hudayriyat Island, Modon, read Nov 12, 2026
- Modon Properties reveals Hudayriyat Island masterplan, Modon, Jun 13, 2023
Moments
East Hill Launch - Exclusive Mansions and Villas on Hudayriyat Island
Modon Real Estate
Photos
See also
-
Payment PlanNawayef South's payment plan is not published. Nawayef East, the hill before it, sells on 40/60, 10% down, 30% during construction and 60% on handover, which is AED 2.64M before handover on a AED 6.6M Home. Modon lists four different splits across Hudayriyat Island. -
How to Register InterestNawayef South cannot be booked yet. Until Modon opens sales, expected in December 2026 by what it told the broker Emigeo, a buyer can register with Modon directly or with a broker, at no cost and with no home reserved. Abu Dhabi now routes paid expressions of interest through a government platform. -
Prices and Home TypesNawayef South has no published prices. For reference, Modon lists Nawayef East Homes from AED 6.6M and Heights from AED 19.3M, which we work out at about AED 1,657 and AED 1,498 per square foot of built-up area, across 19 designs from 370 to 3,484 sq m.